All Roofing / Siding / Gutters / Windows / Doors have been isntalled.
All repairs made to the frame of the property. All burned sections were removed.
All repairs made to the frame of the property. All burned sections were removed.
Interior framing is complete.
New Electrical service was installed! (inspection passed!)
DigSafe (811) was called and grounds were marked so we don't hit any underground pipes, wires etc.. when digging for footings. Front Porch has not been rebuilt as we're waiting on the Plymouth Building department and Zoning to approve our plans.
This week we're working on Rough Electrical, Rough Plumbing and HVAC.
STAY TUNED FOR MORE on 35 Cherry Street, Plymouth, Ma renovation.